Edinboro University
Edinboro , Pennsylvania

 

Upgrade campus wide electrical distribution system. Contract duration was one year; this project was started and completed in 1999. The value of this contract was $2,400,000.00.

Work Description:

Complete upgrade of electrical distribution system from 5 KV to 15 KV, work included excavation and backfill for new duct bank system. Medium voltage cable installation, splices and terminations. Installation of new 15 KV pad mounted switches and transformers, selective masonry and concrete work.

All work was completed while the college was active. Major power outages and cutovers were accomplished nights and weekends to allow the college to operate during the day.

 
         